Sewer Collection SystemBlair Township, Michigan
Map View
Gosling Czubak provided engineering services from inception to the completion of Blair Township’s sewer system. Work included planning, preliminary engineering, facilitating the public process, designing, permitting, assisting development of special assessment and rate structures, acquiring easements, and providing construction engineering, stakeout and materials testing. The sewer system includes 10 miles of gravity sewer, 5 miles of force main and a pumping station expandable to 1 MDG. The total project cost was approximately $4.5M.
What our Clients Say
Related News
August 16, 2021
Eric Vincke Certified as Drinking Water Operator
July 19, 2021
New Biosolids Sampling Requirements